MAIN STAGES OF THE STADIUM PROJECT
Based on information from the Trust’s June 2007 progress report
Main stages of the project | Timeframes |
---|---|
Vision | June to August 2006 |
Preliminary feasibility | July 2006 to June 2007 |
Master Plan and Feasibility | September 2006 to March 2007 |
Public funding and consultation | March 2007 to July 2008 |
Private funding sources | July 2007 to December 2007 |
Site acquisition | May 2007 to August 2008 |
Plan change and resource consents | April 2007 to August 2008 |
Design and construction (including concept design, developed design, construction procurement, construction) |
June 2007 to April 2011 |