MAIN STAGES OF THE STADIUM PROJECT

Based on information from the Trust’s June 2007 progress report

Main stages of the project Timeframes
Vision June to August 2006
Preliminary feasibility July 2006 to June 2007
Master Plan and Feasibility September 2006 to March 2007
Public funding and consultation March 2007 to July 2008
Private funding sources July 2007 to December 2007
Site acquisition May 2007 to August 2008
Plan change and resource consents April 2007 to August 2008
Design and construction
(including concept design, developed design, construction procurement, construction)
June 2007 to April 2011