Part 5: Life cycle costing analysis
Introduction
5.1
In this Part we:
- explain life cycle costing analysis;
- discuss the analysis used by the Defence agencies to estimate the ongoing costs associated with the LAV project; and
- examine how life cycle costing analysis has been introduced to the Defence agencies, and how it is being used in relation to the generic military capability acquisition process.
Background
What is life cycle costing analysis?
5.2
Life cycle costing analysis identifies and documents all the costs involved
throughout the life of a military capability.41 These include the cost of the initial
acquisition of the equipment, and the amount required to operate, maintain, and
eventually dispose of the equipment.
5.3
Life cycle costing analysis is important, and needs to be undertaken to give the
Government the best possible estimate of the ongoing costs associated with a
new military capability at the time the decision is made to approve the
acquisition of equipment. It is also necessary for making accurate operating
baseline adjustments throughout the life of the equipment.
Our first report
5.4
Our August 2001 report found that the capability requirements necessary for
the Army to maintain 105 LAVs had not been fully assessed, costed, or
provided for.
5.5
We also noted that there was doubt over the accuracy of the estimated annual
operating costs of the LAVs. In January 2001, the steady-state annual operating
costs were estimated to be $39 million42 for the life of all the vehicles.
Use of life cycle costing analysis
Life cycle costing analysis for the Light Armoured Vehicle project
5.6
In December 2001, Army Finance personnel began using life cycle costing
analysis to conduct an in-depth study of the operating costs of the LAV.
5.7
The Army experienced difficulties obtaining the performance data required to
perform its analysis. This was because the LAV is a relatively new piece of
military equipment, so only limited performance data is available. In addition,
there were communication problems between the Army and MoD (Acquisition)
that we identified in our first report.
5.8
The Army obtained performance data43 from General Dynamics and the
Canadian and Australian armies (which have similar vehicles), and adjusted
that data for New Zealand conditions. This information was used for Army
Finance’s life cycle costing analysis, and to update the cost estimates included
in the Army’s Five Year Operating Plan.
5.9
The 2003-04 version of the Army’s Five Year Operating Plan estimated the
steady-state annual operating costs of the LAVs as $48.8 million a year. This is
$9.8 million a year more than was estimated in January 2001. Depreciation
accounts for a major portion of the cost estimate.
5.10
The Army’s current estimated annual operating costs (for the 5-year period
2003-04 to 2007-08) are shown in Figure 9 on the next page. The current
steady-state figure is from 2007-08 onwards.
5.11
The Army considers that it will take at least 2 years of LAV use in New
Zealand to collect enough performance data to produce more reliable cost
estimates.
Figure 9
Current estimated annual operating costs for
105 Light Armoured Vehicles
|
2003-04 Actual $m |
2004-05 $m |
2005-06 $m |
2006-07 $m |
2007-08 $m |
2008-09 $m |
---|---|---|---|---|---|---|
Repairs and maintenance | 0.0 | 7.5 | 8.6 | 9.4 | 10.0 | 10.0 |
Fuel, tyres, etc. | 0.2 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 |
Ammunition for training | 0.6 | 2.5 | 2.7 | 2.5 | 2.7 | 2.7 |
Logistic Support Agreement | 1.4 | 2.5 | 2.2 | 2.1 | 2.1 | 2.1 |
Gross operating costs | 2.2 | 12.9 | 13.9 | 14.4 | 15.2 | 15.2 |
Less savings* | (1.0) | (1.0) | (1.5) | (1.5) | (1.5) | (1.5) |
Net operating costs | 1.2 | 11.9 | 12.4 | 12.9 | 13.7 | 13.7 |
Depreciation | 1.3 | 11.1 | 30.3 | 35.1 | 35.1 | 35.1 |
Ownership costs** | 2.5 | 23.0 | 42.7 | 48.0 | 48.8 | 48.8 |
* Related to reassignment of operating costs of the M113 and Scorpion vehicles that the LAV is replacing.
** The figures of $48.8 million for 2007-08 and 2008-09 reflect the ongoing steady-state costs for annual operation and maintenance of the 105 LAVs.
5.12
In our view, the Army followed a reasonable process in identifying the costs of
operating and maintaining the LAVs to include in the Five Year Operating Plan
through to 2008-09. However, the life cycle costing analysis for the LAV
project has not yet been fully completed, and the costs have not been
extrapolated for the life of the LAVs.
Introduction of life cycle costing analysis into the Defence agencies
5.13
In September 2002, the Chief of Defence Force issued Defence Force Order
10/2002, obliging the NZDF and the single armed services to use life cycle
costing analysis as part of the military capability acquisition process.44
5.14
The Defence Force Order applied to the LAV project, so a full life cycle costing
analysis should have been completed for the LAVs by now (and not just a 5-year estimate).
5.15
In December 2003, the Foreign Affairs, Defence and Trade Select Committee
reported on the 2002-03 Financial Review of the MoD and the NZDF. The
Committee noted that life cycle costing is a crucial part of decision-making in
regard to capability acquisition.
5.16
Life cycle costing analysis for all military capability acquisition projects was
made compulsory for all of the Defence agencies when the Capability
Management Framework was formally signed by the Secretary of Defence and
the Chief of Defence Force in April 2004. The Capability Management Framework requires life cycle costing to be undertaken in accordance with the
Defence Force Order.
Have the requirements of the Defence Force Order been met with respect to LAVs?
5.17
As noted in paragraph 5.6, the Army began using life cycle costing analysis of
the LAVs in December 2001 – before the September 2002 Defence Force Order
that made the use of life cycle costing mandatory throughout the NZDF.
5.18
Under the Defence Force Order, the Army must identify the cost implications
of actual or planned modifications, upgrades or life extensions. This has not yet
been done for the LAVs.
5.19
The Defence Force Order also notes that, historically, insufficient focus has
been given to costs associated with disposal of military equipment. The Army’s
life cycle costing analysis for the LAVs does not include likely disposal costs.
5.20
The Defence agencies informed us that their ability to make any meaningful
assessment of upgrades to the LAVs, or the costs of disposal, is very limited, as
these events are many years away.
5.21
We acknowledge that there may be difficulties at times in obtaining reliable
data on which to base life cycle costing analysis. However, any limitations in
the analysis, and assumptions made around it, can be highlighted at the time the
analysis is presented to decision-makers.
5.22
We note the effort of the Defence agencies in relation to the introduction of life
cycle costing analysis45. Those involved in using the analysis process told us
that there has been an increase in commitment by all of the Defence agencies to
use life cycle costing analysis for acquisitions. They said that this has resulted
in better working relationships between key people, and an improvement in the
quality of the data obtained and its subsequent analysis. It has been a positive
step forward from the communication problems (see paragraph 5.7) that existed
when the Army was carrying out its in-depth study of LAV operating costs.
Recommendation
Recommendation 9 |
---|
We recommend that life cycle costing analysis be completed for the Light Armoured Vehicle project, as required by the Capability Management Framework, including a calculation of the whole-of-life costs for the 105 LAVs. These costs should continue to be monitored throughout the life of the LAVs in order to assist with re-adjusting operating baselines. |
41: These costs are known as the through-life costs of a capability, and also as the total cost of ownership of a capability.
42: The January 2001 paper seeking the approval of the Ministers of Finance and Defence estimated the annual operating cost for the LAVs at $39 million a year (including depreciation of about $30 million a year) over the 25-year life of the vehicles.
43: The data included the number of training kilometres each vehicle travelled, the amount of ammunition required for training, failure rates of parts, and the average cost of repairs.
44: The MoD was not covered by this order, as Defence Force Orders apply only to the NZDF.
45: For example, a Life Cycle Costing Analysis Cell was established in the NZDF Resources Branch to act as a centre of excellence for life cycle costing analysis. Also, about 250 people from throughout the Defence agencies have attended life cycle costing analysis training courses.
page top